Dalekovod signed contracts in Slovenia worth almost HRK 450 million

19.06.2020.

In Ljubljana today, Dalekovod signed contracts for two interconnected projects with the company Eles d.o.o., Slovenian national operator of the electricity transmission system.
The larger project, Cirkovce - Pince, includes the construction of a total of 80 kilometers long, new double 400 kV transmission line and will be completed in 2022, while works on the reconstruction and construction of 220 kV transmission line Cirkovce - Žerjavinec are scheduled for the second part of 2020. Upon completion, sections will connect Hungarian and Slovenian transmission networks at a voltage level of 400 kV and thus increase the capacity of both transmission systems and provide preconditions for future energy projects.
New contracts continue the presence of the Dalekovod Group on the Slovenian market, where preparatory works are already underway for the reconstruction of the double 400 kV transmission line Beričevo - Okroglo with a total length of 32.5 kilometers.
The projects will be carried out by a consortium in which, in addition to the holder, Dalekovod Ljubljana d.o.o. includes Elektrotehna Elex d.o.o. and C&G d.o.o. The total value of works on all three projects, which should be realized by 2022, is almost 450 million kuna.
to the top